There are three ways to mass complete task:

  1. Hold SHIFT and select the first Task. This will bulk select all the task in the view. 

  2. Hold SHIFT and select the last Task in a list of task you would like to mass complete. This will bulk select the last task and all the task that come before it.

  3. Hold CMD/CTRL and individually select the task you would like to complete. This will bulk select just those task you selected. 